What this standard covers
Essential erection tolerances cover column plumb, level and position on grid; they are measured against the erected frame before the structure is handed over for follow-on trades.
Essential erection tolerances cover column plumb, level and position on grid; they are measured against the erected frame before the structure is handed over for follow-on trades.
Who uses it
Erection engineers, site managers and temporary works coordinators planning safe steel erection.
Details
Reference data
- Standard number
- Erection tolerances
- Title
- Erection tolerance and setting out practice
- Organisation
- StructuralSteel.ai reference
- Country
- International
- Region
- international
- Subject
- Erection
- Subcategory
- Practice
- Type
- INDUSTRY BEST PRACTICE
- Application
- Contractual
- Availability
- Free
- Status
- CURRENT
- Roles
- erection standard
- Last verified
- 2026-09-06
Official source: steelconstruction.info
Related
Standards used alongside this one
- BS EN 1090-2
Execution of steel structures — Technical requirements for steel structures
The central execution standard for UK and European steelwork: execution classes EXC1 to EXC4, constituent products, cutting and holing, welding, bolting, erection and geometrical tolerances.
United KingdomFabricationCURRENTPaid
- AISC 303
Code of Standard Practice for Steel Buildings and Bridges
Defines the customary trade practices: scope of supply, drawing responsibilities, mill and fabrication tolerances, and erection tolerances for the structural steel frame.
United StatesFabricationCURRENTFree
- 29 CFR 1926 Subpart R
OSHA Safety Standards for Steel Erection
Federal steel erection safety rules covering column anchorage, connection practice, decking, fall protection and site sequencing.
United StatesErectionCURRENTFree
- BS 5975
Code of practice for temporary works procedures and the permissible stress design of falsework
The temporary works management framework, including the temporary works coordinator role that governs stability during steel erection.
United KingdomErectionCURRENTPaid
- CDM 2015
Construction (Design and Management) Regulations 2015
UK construction health and safety law setting duties for clients, designers, principal contractors and contractors, including erection planning.
United KingdomErectionCURRENTFree
- IS 7205
Safety Code for Erection of Structural Steelwork
Safety requirements for erecting structural steelwork including lifting, temporary bracing and access.
IndiaErectionCURRENTPaid
Sourcing, review and use
Status
Editorial reference information compiled and maintained by the StructuralSteel.ai team. It is not a design certificate and is not issued under an engineer's seal.
Last reviewed
Calculations
Any figures produced on this page are indicative estimates for early sizing and comparison only — they are not engineered design outputs.
References
Final member selection, loading, connection design, fire design, fabrication and compliance must be verified for your specific project by a suitably qualified structural engineer. Standards are revised; check the edition in force where the work is built.
Verification
StructuralSteel.ai provides technical reference information and links to authoritative sources. Project specifications, applicable legislation, current standards editions and requirements of the responsible engineer or authority should always be verified before fabrication or supply.